OVERHEAD LINE (MV & LV NETWORK)

Bromine Power Plant:

                                

 
Projects Reference List:
1-

RURAL ELECTRIFICATION- WESTBANK(PALESTINE)

2 YEARS

Turn Key Project.

 

2-

BROMINE POWER PLANT

JORDAN BROMINECOMPANY

2001

Turn Key Project.
3-

MGO POWER PLANT

JORDAN MAGNESIA COMPANY

1999-2000

Turn Key Project
4-

ELECTRIFICATION OF AL - SAMEK AREA & PHASE 2 EXPANSION PROJECTS.

JORDAN ELECTRIC POWER CO.

6 MONTHS 1988

Turn Key Project

5-

MV DISTRIBUTION NETWORK

JORDAN ELECTRIC POWER CO.

4 MONTH 1987

INSTALLATION, TESTING AND COMMISSIONING OF MV DISTRIBUTION NETWORK FOR THE MAIN ELECTRIC POWER CO, IN JORDAN / AMMAN AREA.THE WORK COMPRISES THE INSTALLATION OF 50 KM, 33KV OVERHEAD LINE COMPLETE WITH ALL ACCESSORIES.

6-

RURAL ELECTRIFICATION

JORDAN ELECTRIC POWER

CO.

12 MONTHS

1986

COMPLETE ERECTION, TESTING COMMISSIONING AND MAINTENANCE OF DISTRIBUTION NETWORKS FOR ELECTRIFICATION OF 11 VILLAGES.THE WORKS, INCLUDED THE FOLLOWINGS:

80 KM 33 k V OVERHEAD LINE

20 KM 11 kV OVERHEAD LINE

2000 LV POLES.

30 POLE MOUNTED SUBSTATION.

7-

RURAL ELECTRIFICATION

JORDAN ELECTRIC POWER CO.

8 MONTHS1985

COMPLETE, ERECTION, TESTING COMMISSIONING AND MAINTENANCE FOR ELECTRIFICATION OF 7 VILLAGES.THE PROJECT COMPRISES THE FOLLWING:

40 KM 33 kV OVERHEAD LINE

15 KM 11 kV OVERHEAD LINE

1200 LV POLES

15 POLE MOUNTED DISTRIBUTION SUBSTATION.

  
 